Drill small reference hole under location of VacPan™ to determine position in basement or crawl space. 2. Using a hole saw, cut access hole (3) in floor under cabinet. Position access hole (3) so that final fittings (7) can be installed by reaching through access hole (3). 3. Cut 6 3/4" long slot along kick (4) of cabinet. 4. Make terminal connections (5). 5. Slide VacPan™ (6) into slot and secure using #6 painted wood screws provided. 6. Reach through access hole (3) and make final fitting connections (7). IF ACCESS CANNOT BE MADE FROM BELOW 1. Rough-in pipe (8) through floor, provide 1/2" play in pipe. 2. Provide slack in low voltage lines for future connection. 3. Once cabinets are installed, cut access hole (13) and cover with cover plate (14). Reach through and make final connections as per previous installation. \-IF CEILING IS INSTALLED - PROVIDE COVER PLATE IN BOTTOM OF CABINET TO MAKE FITTING CONNECTIONS. (IF CEILING IS NOT INSTALLED, FINAL FITTING CONNECTIONS CAN BE MADE THROUGH ACCESS HOLE IN FIGURE 2 SUBFLOOR. INSTALLATION OPTION #2 - IN WALLS ALONG BASE BOARDS Refer to Figure 3 (ACCESS TO PIPING FROM BELOW) 1. Locate studs (1) in the wall at the location VacPan™ will be installed. 2. VacPan™ should be located tight to one side in stud space. 3. Drill a small reference hole (2) through the floor under area of VacPan™. This will establish location from basement. 4. From below, use hole saw to remove wood floor and wood plate at location of VacPan™ between studs in wall cavity to provide access hole (3) from below. 5. Using a 11/2" hole saw, remove a 6 3/4" long slot (4) in baseboard tight to one stud. FIGURE 3 Refer to Figure 4 6. Make wire connections to brass terminal and sprig terminal screws (5). 7. Secure VacPan™ (6) to baseboard using #6 screws provided. 8. From below, reach through hole (3) in stud space and push elbow (7) onto VacPan™ (6). 9. Make piping connections (8) as required to tie into existing central vac piping. FIGURE 4 INSTALLATION NEW HOME CONSTRUCTION Refer to Figure 5 1. Cut out wall plate (9) between two studs at the location of VacPan™. Cut a 6 3/4" piece of wall plate and refasten to floor temporary rough-in block. (10) This will act as temporary rough-in block that will force all trades to finish around providing a slot in wall for installation of VacPan™. Make certain that screws (11) remain exposed so that block can be removed in the future. 2. Flooring contractor must run flooring under block. 3. Rough-in pipe and low voltage leads (12) to location of VacPan™ outlet. Ensure final fitting is installed 1“ off finished floor with 1/2n of play in piping to allow VacPan™ to be slid into position. FIGURE 5 Refer to Figure 5 1. If ceiling is installed below and access to pipe is not possible, cut 2 3/4" X 4 1/2" access hole (13) in wall above VacPan™ (6). Reach through access hole, lift pipe and slide VacPan™ into position and push elbow onto VacPan™. 2. Cover access hole with cover plate (14). FIGURE 6 Product specifications subject to change without notice. NuTone 4820 Red Bank Road, Cincinnati, Ohio 45227 1140 Tristar Drive, Mississauga, Ontario, Canada L5T1H9 Printed in U.S.A., Rev. 3/02...